Goliat Gas Export CNG Project

Status: Completed

Scope of Work

Feasibility Study

Project Description

​​​​CNG Project for Goliat Field Gas production delivery.  Engineering services for loading and unloading facilities

Technical Details

Type of plant: Transfer line for CNG unloading system

Engineering man-hours: 8.800

Water Depth: 650 ft


  • Gas 1,2 @ 3,0 MSm3/day

Operating pressure: 93-107 barg

Temperature: -15/+60 °C​